Plant implementationFlare relocation by helicopter in the Bernese Oberland
As part of the implementation of the new biogas storage tank at Oberland Energie AG in Spiez, a project planned by B+T Engineering AG, the existing gas flare had to be relocated due to space constraints.
A helicopter was used for the transport. This approach eliminated the need to build a complex lifting and transport structure. It also resulted in significant time savings, as the entire transport took only 30 minutes.